Rehabilitation And Catchment Conservation Of Ikaasu Earthdam

Completed GoMC-PMTS-2025-3410
Project Description
  • Preparation of embankment and breach section
  • Backfilling of breach section with compaction
  • Raising of the embankment wall by 1 meter
  • Desilting of the dam
  • Relocation of spillway from LHS to RHS
  • Construction of 26 gabion units
  • Stone pitching works covering 60 m²
Budget & Expenditure
Approved
KES 5.00M
Contract
KES 0.00
Spent
KES 4.29M
Utilisation
85.8%
Budget Utilisation
Gallery (3 photos)
Before The Works
Before The Works
Before The Repair
Before The Repair
Ongoing Works
Ongoing Works
Citizen Feedback
Japheth Ondieki 02 Apr 2026
Rehabilitation And Catchment Conservation Of Ikaasu Earthdam

What Was The Actual Cost For The Project

Official Response:

Kindly note that the budget allocated for project was Kshs.5 million. For more information please refer to the project details provided. Thank you

Project Details
  • RefGoMC-PMTS-2025-3410
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateMakueni County Sand Conservation and Utilization Authority
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Dec 2025
  • End27 Feb 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Sep 2025
Approved Requisition
Phase Two · 05 Sep 2025
Floated
Phase Two · 24 Sep 2025
Awarded
Phase Two · 09 Oct 2025
Site Handover
Phase Three · 28 Oct 2025
Not Started
Phase Three · 24 Dec 2025
Ongoing
Phase Three · 01 Dec 2025
Completed
Phase Three · 18 Dec 2025