Opening And Unclogging Of Drainage Systems

Completed GoMC-PMTS-2024-8087
Project Description
  • Construction of storm water drains 
  • Installation of culverts 
Budget & Expenditure
Approved
KES 1.20M
Contract
KES 1.20M
Spent
KES 1.20M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8087
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateWote Municipality
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start09 Feb 2024
  • End30 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 08 Dec 2023
Approved Requisition
Phase Two · 11 Dec 2023
Floated
Phase Two · 13 Dec 2023
Awarded
Phase Two · 25 Jan 2024
Site Handover
Phase Three · 09 Feb 2024
Not Started
Phase Two · 12 Feb 2024
Ongoing
Phase Three · 12 Feb 0024
Completed
Phase Three · 19 Feb 2024