Kithamba Borehole -solarization And Extension Of Pipeline To Kinyuani Areas

Ongoing GoMC-PMTS-2025-1904
Project Description
Kithamba Borehole  -Solarization and extension of pipeline to kinyuani areas
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.87M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-1904
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start03 Dec 2025
  • End03 Feb 2026
Timeline
Cabinet Paper Approved
Phase One · 17 Sep 2025
Approved Requisition
Phase Two · 22 Oct 2025
Floated
Phase Two · 05 Nov 2025
Awarded
Phase Two · 01 Dec 2025
Site Handover
Phase Three · 05 Dec 2025
Not Started
Phase Three · 05 Dec 2025
Ongoing
Phase Three · 08 Dec 2025