Thwake Sand Dam Water Project -construction Of Sump, Pumping, Distribution Tank (50m3), Pumping Line And Distribution Line To Uvaani

Ongoing GoMC-PMTS-2025-5680
Project Description
Thwake sand dam water project -Construction of sump, pumping, distribution tank (50M3), pumping line and distribution line to Uvaani
Budget & Expenditure
Approved
KES 7.00M
Contract
KES 727.5K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-5680
  • WardTulimani
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Nov 2025
  • End27 Jan 2026
Timeline
Cabinet Paper Approved
Phase One · 01 Oct 2025
Approved Requisition
Phase Two · 22 Oct 2025
Floated
Phase Two · 28 Oct 2025
Floated
Phase Two · 28 Oct 2025
Awarded
Phase Two · 25 Nov 2025
Site Handover
Phase Three · 30 Nov 2025
Not Started
Phase Three · 30 Nov 2025
Ongoing
Phase Three · 02 Nov 2025