Borehole Drilling -borehole To Supply Water To Ivoleni Area

Ongoing GoMC-PMTS-2025-9098
Project Description
Borehole Drilling -Borehole To Supply water to Ivoleni Area
Budget & Expenditure
Approved
KES 1.80M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9098
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Oct 2025
  • End30 Nov 2025
Timeline
Cabinet Paper Approved
Phase One · 02 Aug 2025
Approved Requisition
Phase Two · 22 Sep 2025
Floated
Phase Two · 02 Oct 2025
Awarded
Phase Two · 24 Oct 2025
Site Handover
Phase Three · 27 Oct 2025
Not Started
Phase Three · 27 Oct 2025
Ongoing
Phase Three · 28 Oct 2025