Itumbule Dispensary – Fencing, Wiring, And Construction Of Soak Pit, Ash Pit And Incinerator At Itumbule Dispensary.

Completed GoMC-PMTS-2024-5834
Project Description

 Fencing, wiring, and construction of soak pit, ash pit and incinerator at Itumbule Dispensary. 

Budget & Expenditure
Approved
KES 1.27M
Contract
KES 1.19M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (3 photos)
Itumbule Fencing And Installation Of Gate
Itumbule Fencing And Installation Of Gate
Itumbule
Itumbule
Itumbule
Itumbule
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5834
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start13 Feb 2024
  • End15 May 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 03 Jan 2024
Floated
Phase Two · 06 Jan 2024
Awarded
Phase Two · 12 Feb 2024
Site Handover
Phase Three · 18 Feb 2024
Not Started
Phase Two · 18 Feb 2024
Ongoing
Phase Three · 20 Feb 2024
Completed
Phase Three · 22 Apr 2024