Extension Of Ndumoni Borehole Pipeline

Under Procurement GoMC-PMTS-2025-6438
Project Description
Extension of Ndumoni Borehole pipeline
Budget & Expenditure
Approved
KES 600.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6438
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Mar 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 12 Sep 2025
Approved Requisition
Phase Two · 30 Oct 2025
Floated
Phase Two · 20 Nov 2025
Awarded
Phase Two · 09 Mar 2026