Kwa Ndule Water Sum(new Project) -construction Of Sump And Distribution Of Water To Kasevini

Ongoing GoMC-PMTS-2025-2690
Project Description
Kwa Ndule Water Sum(New Project) -Construction of sump and distribution of water to Kasevini
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 1.72M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-2690
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start06 Jan 2026
  • End20 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Oct 2025
Approved Requisition
Phase Two · 29 Oct 2025
Floated
Phase Two · 26 Nov 2025
Awarded
Phase Two · 05 Jan 2026
Site Handover
Phase Three · 13 Jan 2026
Not Started
Phase Three · 13 Jan 2026
Ongoing
Phase Three · 13 Jan 2026