Kwa Ndule Water Sum(new Project) -construction Of Sump And Distribution Of Water To Kasevini
Home
Projects
Detail
Ongoing
GoMC-PMTS-2025-2690
Print
Share
Project Description
Kwa Ndule Water Sum(New Project) -Construction of sump and distribution of water to Kasevini
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 1.72M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2025-2690
Ward
Nzaui/Kilili/Kalamba
Sub-County
Makueni
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2025/2026
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
06 Jan 2026
End
20 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Oct 2025
Approved Requisition
Phase Two · 29 Oct 2025
Floated
Phase Two · 26 Nov 2025
Awarded
Phase Two · 05 Jan 2026
Site Handover
Phase Three · 13 Jan 2026
Not Started
Phase Three · 13 Jan 2026
Ongoing
Phase Three · 13 Jan 2026
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement