"kwa Malika Sump Rehabilitation, Solarization And Distribution -sump, Rehabilitation, Solarization, Equipping Distribution Line To Kitende,kwa Mtungu And Mii Rehabilitation Of Itulu Line"

Ongoing GoMC-PMTS-2025-5566
Project Description
Kwa Malika Sump Rehabilitation, solarization and distribution -Sump, rehabilitation, solarization, equipping
Distribution line to Kitende,Kwa Mtungu and Mii
Rehabilitation of Itulu line
Budget & Expenditure
Approved
KES 3.50M
Contract
KES 2.96M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-5566
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start07 Jan 2025
  • End20 Mar 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Oct 2025
Approved Requisition
Phase Two · 30 Oct 2025
Floated
Phase Two · 18 Nov 2025
Awarded
Phase Two · 05 Jan 2025
Site Handover
Phase Three · 12 Jan 2026
Not Started
Phase Three · 12 Jan 2026
Ongoing
Phase Three · 12 Jan 2026