Yikivumbu Borehole-drilling And Distribution Drilling,test-pumping,solarization, Equipping And Distribution

Completed GoMC-PMTS-2025-2778
Project Description
Yikivumbu borehole-Drilling and distribution drilling,test-pumping,Solarization, equipping and distribution
Budget & Expenditure
Approved
KES 3.50M
Contract
KES 0.00
Spent
KES 3.50M
Utilisation
100%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
Borehole drilling KES 1.00M KES 0.00 Not Started
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-2778
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Aug 2025
Approved Requisition
Phase Two · 19 Sep 2025
Ongoing
Phase Three · 25 Sep 2025
Completed