Kikima Water Project -rehabilitation Of Pipeline, Servicing Of Pumps, Desilting And Improvement Of Water Weir

Ongoing GoMC-PMTS-2025-6194
Project Description
Kikima Water Project -Rehabilitation of pipeline, servicing of pumps, desilting and improvement of water weir
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6194
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Feb 2026
  • End20 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 29 Jan 2026
Approved Requisition
Phase Two · 02 Feb 2026
Floated
Phase Two · 05 Feb 2026
Awarded
Phase Two · 08 Feb 2026
Site Handover
Phase Three · 12 Feb 2026
Not Started
Phase Three · 12 Feb 2026
Ongoing
Phase Three · 18 Feb 2026