Kativani Borehole -rehabilitation, Purification And Distribution
Home
Projects
Detail
Ongoing
GoMC-PMTS-2025-2805
Print
Share
Project Description
Kativani borehole -Rehabilitation, purification and Distribution
Budget & Expenditure
Approved
KES 7.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2025-2805
Ward
Masongaleni
Sub-County
Kibwezi East
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2025/2026
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
12 Feb 2026
End
20 May 2026
Timeline
Cabinet Paper Approved
Phase One · 29 Jan 2026
Approved Requisition
Phase Two · 02 Feb 2026
Floated
Phase Two · 05 Feb 2026
Awarded
Phase Two · 08 Feb 2026
Site Handover
Phase Three · 12 Feb 2026
Not Started
Phase Three · 12 Feb 2026
Ongoing
Phase Three · 18 Feb 2026
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement