Matinga 1 Dam -additional Solar, Plastic Elevated Tank-24m3, Rehabiliation Of The Rising Main And Distribute Water To Ikaasu,kwa Kilai And Ituka Villages

Ongoing GoMC-PMTS-2025-6870
Project Description
Matinga 1 dam -Additional solar, Plastic elevated tank-24M3, Rehabiliation of the rising main and distribute water to Ikaasu,kwa Kilai and Ituka Villages
Budget & Expenditure
Approved
KES 3.00M
Contract
KES 2.85M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6870
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start16 Dec 2025
  • End16 Feb 2026
Timeline
Cabinet Paper Approved
Phase One · 17 Sep 2025
Approved Requisition
Phase Two · 22 Oct 2025
Floated
Phase Two · 10 Nov 2025
Awarded
Phase Two · 09 Dec 2025
Site Handover
Phase Three · 16 Dec 2025
Not Started
Phase Three · 16 Dec 2025
Ongoing
Phase Three · 20 Dec 2025