Fencing Of Kwa-kotoe Dispensary (katune Disp)

Completed GoMC-PMTS-2024-7901
Project Description

Chainlink fencing of the facility

Budget & Expenditure
Approved
KES 980.0K
Contract
KES 947.7K
Spent
KES 651.8K
Utilisation
66.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7901
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start03 Dec 2023
  • End03 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 05 Nov 2023
Floated
Phase Two · 08 Nov 2023
Awarded
Phase Two · 30 Nov 2023
Awarded
Phase Two · 30 Nov 2023
Site Handover
Phase Three · 04 Dec 2023
Not Started
Phase Two · 04 Dec 2023
Ongoing
Phase Three · 06 Dec 2023
Completed
Phase Three · 08 Jan 2024