Solarization And Equipping Of Makutano Borehole And Distribution Of Water

Ongoing GoMC-PMTS-2025-4679
Project Description
Solarization and Equipping of Makutano borehole and distribution of water
Budget & Expenditure
Approved
KES 5.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4679
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start18 Feb 2026
  • End20 May 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2025
Approved Requisition
Phase Two · 29 Oct 2025
Floated
Phase Two · 20 Jan 2026
Awarded
Phase Two · 13 Feb 2026
Site Handover
Phase Three · 16 Feb 2026
Not Started
Phase Three · 16 Feb 2026
Ongoing
Phase Three · 18 Feb 2026