Roads Maintenance Fuel Levy

Ongoing GoMC-PMTS-2025-9197
Project Description

The programme entails routine maintenance, periodic maintenance and spot improvement  works on 17No. Project roads listed in the attachment. The overall scope of works to be executed include; opening/ widening of 42.90 km roads, grading of  203.80 km, Graveling of 42.90Kms, construction of 13No. Drifts/ Slabs (585m in length), installation of 574m of culverts, installation of 204 gabion as protection works,   and excavation of catch water drains amounting to 8,600M3

Budget & Expenditure
Approved
KES 355.58M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Components (17)
Component Budget Expenditure Status
Mantainance And Fuel Levy KES 4.96M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 4.20M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 6.06M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 7.44M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 9.59M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 9.84M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 3.96M KES 3.96M Completed
Mantainance And Fuel Levy KES 13.13M KES 0.00 Null
Mantainance And Fuel Levy KES 9.47M KES 0.00 Ongoing
Kikima Town-kyuu-kwa Nzei-ukala-matondoni-mandei Road KES 10.74M KES 0.00 Ongoing
mantainance and fuel levy KES 15.18M KES 0.00 Null
Mantainance And Fuel Levy KES 7.41M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 4.97M KES 0.00 Null
Mantainance And Fuel Levy KES 3.13M KES 3.13M Completed
Mantainance And Fuel Levy KES 9.52M KES 0.00 Ongoing
Mantainance And Fuel Levy KES 17.11M KES 0.00 Ongoing
Mukaa - Uvete road KES 5.24M KES 0.00 Ongoing
Gallery (7 photos)
Ongoing Zion -utithi- Kikunduku- Nzouni-metava-bosnia-kasasule Makutano-kithasyu- Sokomoko Game Rd Rehabilitation
Ongoing Zion -utithi- Kikunduku- Nzouni-metava-bosnia-kasasu
12kms Grading Along Kikima Town-kyuu-kwa Nzei-ukala-matondoni-mandei Road
12kms Grading Along Kikima Town-kyuu-kwa Nzei-ukala-matondon
Routine Monitoring Along Kikima Town-kyuu-kwa Nzei-ukala-matondoni-mandei Road
Routine Monitoring Along Kikima Town-kyuu-kwa Nzei-ukala-mat
19kms Road Grading Along Sekeleni - Kwa Mbae - Ngambi Ya Myunzu - Syumile Road
19kms Road Grading Along Sekeleni - Kwa Mbae - Ngambi Ya Myu
Gravelling Along Kiangini-kiteei-kwa  Kinona Rd
Gravelling Along Kiangini-kiteei-kwa Kinona Rd
Bush Clearing Along Kiangini-kiteei-kwa  Kinona Rd
Bush Clearing Along Kiangini-kiteei-kwa Kinona Rd
11.4kms Road Graded Along Imale Primary School Junction-kalawani-mavindu
11.4kms Road Graded Along Imale Primary School Junction-kala
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9197
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start12 Jan 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 04 Sep 2025
Approved Requisition
Phase Two · 29 Sep 2025
Floated
Phase Two · 21 Nov 2025
Awarded
Phase Two · 05 Jan 2026
Site Handover
Phase Three · 12 Jan 2026
Not Started
Phase Three · 12 Jan 2026
Ongoing
Phase Three · 12 Jan 2026