Installation Of Drift At Tutini-kwa Maima Road

Completed GoMC-PMTS-2025-4860
Project Description

Installation of 45M by 6mdrift  and 20 No. gabions along Tutini-Kwa Maima road 

Budget & Expenditure
Approved
KES 5.50M
Contract
KES 0.00
Spent
KES 4.68M
Utilisation
85%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4860
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start08 Dec 2025
  • End14 May 2026
Timeline
Cabinet Paper Approved
Phase One · 16 Sep 2025
Approved Requisition
Phase Two · 17 Sep 2025
Floated
Phase Two · 03 Oct 2025
Awarded
Phase Two · 08 Dec 2025
Site Handover
Phase Three · 07 Jan 2026
Not Started
Phase Three · 07 Jan 2026
Ongoing
Phase Three · 14 Jan 2026
Completed
Phase Three · 02 Mar 2026