Maintainence Of Other Assets - Markets, Tourism Centres.

Completed GoMC-PMTS-2024-5830
Project Description
  • payment of utility bills for market sheds (electricity); Upgrading of  Makongo view point.Kitchen Extension, Construction of washroom with a PWD toilet, Walling with EPS panels, Floor Tiling  and Finishes 
Budget & Expenditure
Approved
KES 263.1K
Contract
KES 3.43M
Spent
KES 1.97M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5830
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Trade, Marketing, Industry, Culture
  • DirectorateTourism
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start29 Feb 2024
  • End30 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 25 Oct 2023
Approved Requisition
Phase Two · 23 Nov 2023
Floated
Phase Two · 15 Dec 2023
Awarded
Phase Two · 26 Jan 2024
Site Handover
Phase Three · 29 Feb 2024
Not Started
Phase Two · 29 Feb 2024
Ongoing
Phase Three · 29 Feb 2024
Completed
Phase Three · 04 Apr 2025