Provision Of Certified Seeds (maize And Beans)adaptive To Mukaa Climate.

Completed GoMC-PMTS-2025-1321
Project Description
 Provision of certified seeds (maize and beans)adaptive to Mukaa climate. -Purchase and distribution of adequate certified seeds(maize and beans). Distribution to be done before the onset of rain season. 


Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 910.4K
Utilisation
30.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-1321
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateAgriculture
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Sep 2025
  • End01 Sep 2025
Timeline
Cabinet Paper Approved
Phase One · 31 Jul 2025
Approved Requisition
Phase Two · 18 Aug 2025
Floated
Phase Two · 18 Aug 2025
Awarded
Phase Two · 01 Sep 2025
Site Handover
Phase Three · 01 Oct 2025
Not Started
Phase Three · 01 Oct 2025
Ongoing
Phase Three · 01 Oct 2025
Completed
Phase Three · 03 Oct 2025