Kavuthu Coldroom

Completed GoMC-PMTS-2024-2387
Project Description

 Operationalization of post harvest facility (cold room pack house) at Kavuthu  in Mbitini ward

Budget & Expenditure
Approved
KES 100.0K
Contract
KES 36.46M
Spent
KES 36.46M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2387
  • WardMbitini
  • Sub-CountyMakueni
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateCooperative Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start24 Jul 2020
  • End25 Sep 2020
Timeline
Cabinet Paper Approved
Phase One · 02 Mar 2020
Approved Requisition
Phase Two · 16 Mar 2020
Floated
Phase Two · 02 Jun 2020
Awarded
Phase Two · 24 Jul 2020
Site Handover
Phase Three · 24 Jul 2020
Not Started
Phase Two · 24 Jul 2020
Ongoing
Phase Three · 24 Jul 2020
Completed
Phase Three · 18 Dec 2020