Renovation Of Ngiini Dispensary

Completed GoMC-PMTS-2025-5950
Project Description

Re roofing Rrepair of wall cracks, tilling, painting and ceiling of the facility

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 0.00
Spent
KES 1.40M
Utilisation
93.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-5950
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Health Services
  • DirectoratePreventive and Promotive Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start23 Jan 2025
  • End23 Jan 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 30 Oct 2024
Floated
Phase Two · 22 Nov 2024
Awarded
Phase Two · 23 Jan 2025
Site Handover
Phase Three · 30 Jan 2025
Not Started
Phase Three · 30 Jan 2025
Ongoing
Phase Three · 30 Jan 2025
Completed
Phase Three · 20 Jun 2025