Drilling And Capping Of Kathamba Borehole

Completed GoMC-PMTS-2025-8872
Project Description

Hydro logical survey

Drilling and capping of Kathamba borehole

Test pumping 

Budget & Expenditure
Approved
KES 1.80M
Contract
KES 0.00
Spent
KES 1.80M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-8872
  • WardKako/Waia
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 20 May 2025
Approved Requisition
Phase Two · 22 May 2025
Ongoing
Phase Three · 25 May 2025
Completed
Phase Three · 15 Jan 2025