Mukaatini Ctti

Completed GoMC-PMTS-2024-6484
Project Description

Construction of a dormitory

Budget & Expenditure
Approved
KES 3.92M
Contract
KES 3.74M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6484
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateTechnical Training
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Feb 2024
  • End28 May 2024
Timeline
Cabinet Paper Approved
Phase One · 25 Oct 2023
Approved Requisition
Phase Two · 07 Nov 2023
Floated
Phase Two · 18 Jan 2024
Awarded
Phase Two · 28 Feb 2024
Site Handover
Phase Three · 28 Feb 2024
Not Started
Phase Two · 01 Mar 2024
Ongoing
Phase Three · 01 Mar 2024
Completed
Phase Three · 23 Jun 2025