Routine Maintenance Of Kathozweni Ward Access Roads

Completed GoMC-PMTS-2025-9514
Project Description

25kms bush clearing , grading and road water harvesting structuctures along Kiteeni junction - mitini kwa Kinona , Kiteei junction 

Budget & Expenditure
Approved
KES 500.0K
Contract
KES 0.00
Spent
KES 457.0K
Utilisation
91.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9514
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Ongoing
Phase Three · 10 Mar 2025
Completed
Phase Three · 23 Jun 2025