Mantainance And Fuelling Ofward Backhoe And Desilting Small Communal Dams Using The Same Machine

Completed GoMC-PMTS-2025-1063
Project Description

mantainance and fuelling ofward backhoe and desilting small communal dams using the same machine

Budget & Expenditure
Approved
KES 3.14M
Contract
KES 0.00
Spent
KES 1.40M
Utilisation
44.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-1063
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 24 Sep 2024
Approved Requisition
Phase Two · 29 Sep 2024
Ongoing
Phase Three · 03 Oct 2024
Completed
Phase Three · 20 Mar 2025