Requisition For Testpumping And Water Analysis For Kwa Wala Borehole

Completed GoMC-PMTS-2025-7006
Project Description

Drilling of the borehole using County machinery

Construction of 2 water kiosks at Kwa Wala and Kwa Kingee

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 0.00
Spent
KES 754.7K
Utilisation
21.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-7006
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 25 Mar 2025
Approved Requisition
Phase Two · 01 Apr 2025
Floated
Phase Two · 23 May 2025
Awarded
Phase Two · 22 Apr 2025
Site Handover
Phase Three · 25 Apr 2025
Not Started
Phase Three · 25 Apr 2025
Ongoing
Phase Three · 25 Apr 2025
Completed
Phase Three · 28 Apr 2025