Syongungi Ecde

Completed GoMC-PMTS-2024-5545
Project Description
  • 2 No. ECDE Classrooms with an office and Store
  • Electrical Works (conduits only)
  • 2 No. Wooden Desks
  • 2 No. Wooden Arm Chairs
  • Water harvesting goods (5,000Ltrs Water Tank and base)
  •  Display Pinned board
  • Branding, Publicity and Signwriting
  • 2 No. Black board
Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.75M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5545
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Mar 2024
  • End12 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 20 Feb 2024
Awarded
Phase Two · 12 Mar 2024
Site Handover
Phase Three · 12 Mar 2024
Not Started
Phase Two · 12 Mar 2024
Ongoing
Phase Three · 12 Mar 2024
Completed
Phase Three · 20 Jun 2024