Ngua/syengoni Brehole- Supply And Delivery Of Drilling Materials

Completed GoMC-PMTS-2025-5212
Project Description

Supply and delivery of drilling materials

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 1.55M
Utilisation
51.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-5212
  • WardAll Wards
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 01 Nov 2024
Approved Requisition
Phase Two · 08 Nov 2024
Floated
Phase Two · 10 Jan 2025
Awarded
Phase Two · 10 Feb 2025
Site Handover
Phase Three · 16 Feb 2025
Not Started
Phase Three · 16 Feb 2025
Ongoing
Phase Three · 18 Feb 2025
Completed
Phase Three · 24 Feb 2025