Kwa Mbuli Borehole Water Project

Completed GoMC-PMTS-2025-1619
Project Description


Installation of a project signboard

Supply of and installation of a surface pump and accessories

Civil works for communal water point infrastructure

Budget & Expenditure
Approved
KES 500.0K
Contract
KES 0.00
Spent
KES 500.0K
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-1619
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start17 Jun 2025
  • End30 Aug 2025
Timeline
Cabinet Paper Approved
Phase One · 28 Mar 2025
Approved Requisition
Phase Two · 02 Apr 2025
Floated
Phase Two · 22 May 2025
Awarded
Phase Two · 16 Jun 2025
Site Handover
Phase Three · 23 Jun 2025
Not Started
Phase Three · 23 Jun 2025
Ongoing
Phase Three · 23 Jun 2025
Completed
Phase Three · 30 Jul 2025