Installation Of Culverts At Chief Ngutu Road

Completed GoMC-PMTS-2025-1136
Project Description

Installation of drainage structure(culvert) at Chief Ngutu road

Budget & Expenditure
Approved
KES 400.0K
Contract
KES 398.7K
Spent
KES 398.8K
Utilisation
99.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-1136
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start24 Mar 2025
  • End22 May 2025
Timeline
Cabinet Paper Approved
Phase One · 29 Jan 2025
Approved Requisition
Phase Two · 29 Jan 2025
Floated
Phase Two · 17 Feb 2025
Awarded
Phase Two · 11 Mar 2025
Site Handover
Phase Three · 24 Mar 2025
Not Started
Phase Three · 24 Mar 2025
Ongoing
Phase Three · 24 Mar 2025
Completed
Phase Three · 24 Apr 2025