Thwake Sump and Distribution Line

Completed GoMC-PMTS-2025-9124
Project Description
Construction of 100cm3 reinforced concrete sump tank, pipeline connection 2050M, construction of 48M3 HOT DIP galvanized steel elevated  water tank , Raising of sand dam well
Budget & Expenditure
Approved
KES 9.17M
Contract
KES 0.00
Spent
KES 3.90M
Utilisation
42.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9124
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Jan 2025
Approved Requisition
Phase Two · 28 Jan 2025
Floated
Phase Two · 06 Feb 2025
Awarded
Phase Two · 24 Apr 2025
Site Handover
Phase Three · 08 May 2025
Not Started
Phase Three · 08 May 2025
Ongoing
Phase Three · 01 May 2025
Completed
Phase Three · 23 Jun 2025