Yiuma Ecde

Completed GoMC-PMTS-2024-2279
Project Description
  • 2 No. ECDE Classrooms with an office and Store
  • Electrical Works (conduits only)
  • 2 No. Wooden Desks
  • 2 No. Wooden Arm Chairs
  • Water harvesting goods (5,000Ltrs Water Tank and base)
  • Display Pinned board
  •   Branding, Publicity and Signwriting
  •   2 No. Black board
Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.79M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (1 photos)
Yiuma Ecde In Nzaui Kilili Kalamba Ward Fy 2023/24
Yiuma Ecde In Nzaui Kilili Kalamba Ward Fy 2023/24
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2279
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Feb 2024
  • End28 May 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 23 Jan 2024
Awarded
Phase Two · 28 Feb 2024
Site Handover
Phase Three · 28 Feb 2024
Not Started
Phase Two · 28 Feb 2024
Ongoing
Phase Three · 04 Mar 2024
Completed
Phase Three · 13 Dec 2024