Ngai Ndethya Water Project

Completed GoMC-PMTS-2025-8913
Project Description

Installation of 8.8kw solar pumping system and accessories

Installation of 2.4km rising main pipeline

Installation of 2No 10 cubic meter plastic water tanks elevated on 6m high steel tower 

Chan link fencing solar structure and water tanks

3.7KM distribution pipeline

Budget & Expenditure
Approved
KES 7.42M
Contract
KES 0.00
Spent
KES 6.70M
Utilisation
90.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-8913
  • WardMtito Andei
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 28 Jan 2025
Approved Requisition
Phase Two · 28 Jan 2025
Approved Requisition
Phase Two · 28 Jan 2025
Floated
Phase Two · 06 Feb 2025
Awarded
Phase Two · 19 Mar 2024
Site Handover
Phase Three · 26 Mar 2025
Not Started
Phase Three · 26 Mar 2025
Ongoing
Phase Three · 31 Mar 2025
Completed
Phase Three · 28 May 2025