Kiusyi Wear Rehabilitation

Completed GoMC-PMTS-2025-4392
Project Description

Kiusyi wear rehabilitation

Budget & Expenditure
Approved
KES 1.48M
Contract
KES 0.00
Spent
KES 1.48M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4392
  • WardIlima
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 18 Mar 2024
Approved Requisition
Phase Two · 25 Mar 2024
Floated
Phase Two · 11 Jun 2024
Awarded
Phase Two · 27 Jun 2024
Site Handover
Phase Three · 30 May 2024
Not Started
Phase Three · 30 May 2024
Ongoing
Phase Three · 05 Jun 2024
Completed
Phase Three · 18 Mar 2024