Rehabilitation Of Kitise Water Project

Completed GoMC-PMTS-2025-6748
Project Description

Rehabilitation of kitise water project

Budget & Expenditure
Approved
KES 8.00M
Contract
KES 0.00
Spent
KES 5.75M
Utilisation
71.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6748
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2024
Approved Requisition
Phase Two · 29 Oct 2024
Floated
Phase Two · 30 Oct 2024
Awarded
Phase Two · 19 Nov 2024
Site Handover
Phase Three · 26 Nov 2024
Not Started
Phase Three · 26 Nov 2024
Ongoing
Phase Three · 20 Dec 2024
Completed
Phase Three · 15 Apr 2025