Mukameni Borehole-purchase And Installation Of Motor

Completed GoMC-PMTS-2025-9034
Project Description

Supply of 2 No submersible pumps and accessories , fencing, piping and plumbing fittings

Budget & Expenditure
Approved
KES 500.0K
Contract
KES 0.00
Spent
KES 500.0K
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9034
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 26 Sep 2024
Floated
Phase Two · 03 Oct 2024
Awarded
Phase Two · 23 Oct 2024
Site Handover
Phase Three · 11 Nov 2024
Not Started
Phase Three · 11 Nov 2024
Ongoing
Phase Three · 20 Nov 2024
Completed
Phase Three · 18 Dec 2024