Equiping And Distribution Of Kwa Mutemwa Borehole

Completed GoMC-PMTS-2025-8200
Project Description

Mobilisation and demobilisation of  plant, equipment and personnel for satisfactory satisfaction of works , equipping of the borehole

Installation of solar power

Construction of Rising main

Construction of 50m3 masonry tank

Construction of borehole chamber and valve chambers

Budget & Expenditure
Approved
KES 6.45M
Contract
KES 0.00
Spent
KES 6.45M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-8200
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 01 Nov 2024
Approved Requisition
Phase Two · 15 Jan 2025
Approved Requisition
Phase Two · 15 Jan 2025
Approved Requisition
Phase Two · 15 Jan 2025
Approved Requisition
Phase Two · 15 Jan 2025
Floated
Phase Two · 24 Jan 2025
Awarded
Phase Two · 25 Feb 2025
Site Handover
Phase Three · 04 Mar 2025
Not Started
Phase Three · 04 Mar 2025
Ongoing
Phase Three · 05 Mar 2025
Completed
Phase Three · 20 Jun 2025