Rehabilitation Of Kwa Mwanzau And Muia Drifts

Completed GoMC-PMTS-2024-6346
Project Description

Construction of a 30m by 6m drift

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 948.3K
Spent
KES 885.9K
Utilisation
88.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6346
  • WardKako/Waia
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Nov 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 15 Oct 2024
Awarded
Phase Two · 12 Nov 2024
Site Handover
Phase Three · 07 Nov 2024
Not Started
Phase Two · 07 Nov 2024
Ongoing
Phase Three · 14 Nov 2024
Completed
Phase Three · 12 Dec 2024