Rehabilitation Of Kwa Sikauti- Kisyulya Road In Kilungu Ward

Completed GoMC-PMTS-2024-3769
Project Description

2.5Kms heavy grading, 1km road graveling, installation of drainage structures such as 600mm dia 22m culvert, 40 gabions and keywalls

Budget & Expenditure
Approved
KES 3.90M
Contract
KES 3.90M
Spent
KES 3.90M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3769
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceEmergency fund
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start28 Oct 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 24 Sep 2024
Floated
Phase Two · 16 Oct 2024
Awarded
Phase Two · 25 Oct 2024
Site Handover
Phase Three · 28 Oct 2024
Not Started
Phase Two · 28 Oct 2024
Ongoing
Phase Three · 04 Nov 2024
Completed
Phase Three · 23 Jan 2025