construction of maternity at masimbani health center

Completed GoMC-PMTS-2024-5000
Project Description

construction of maternity block to completion

electrical works

water harvesting rain water goods, tank base and 5000ltrs water tank

septic tank

soak pit

drainage works

Budget & Expenditure
Approved
KES 4.80M
Contract
KES 0.00
Spent
KES 2.41M
Utilisation
50.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5000
  • WardMasongaleni
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 16 Dec 2024
Approved Requisition
Phase Two · 13 Jan 2025
Floated
Phase Two · 13 Feb 2025
Awarded
Phase Two · 01 Apr 2025
Site Handover
Phase Three · 10 Apr 2025
Not Started
Phase Three · 10 Apr 2025
Ongoing
Phase Three · 10 Apr 2025
Completed
Phase Three · 27 May 2025