Installation Of Fence And Chain Link At Kiboko Dispensary.

Completed GoMC-PMTS-2024-8171
Project Description

CHAIN LINK FENCING

METALIC GATE

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.41M
Spent
KES 1.41M
Utilisation
94.1%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8171
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Jan 2025
  • End10 Jan 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 29 Dec 2024
Floated
Phase Two · 05 Dec 2024
Awarded
Phase Two · 10 Jan 2025
Site Handover
Phase Three · 10 Jan 2025
Not Started
Phase Two · 10 Jan 2025
Ongoing
Phase Three · 20 Jan 2025
Completed
Phase Three · 10 Mar 2025