Construction Of Kivani Staff Quarters

Completed GoMC-PMTS-2024-4806
Project Description

CONSTRUCTION OF STAFF HOUSE-2 BEDROOM

Budget & Expenditure
Approved
KES 3.22M
Contract
KES 0.00
Spent
KES 3.22M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4806
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 16 Dec 2024
Approved Requisition
Phase Two · 13 Jan 2025
Floated
Phase Two · 13 Feb 2025
Awarded
Phase Two · 01 Apr 2025
Site Handover
Phase Three · 07 Apr 2025
Not Started
Phase Three · 07 Apr 2025
Ongoing
Phase Three · 14 Apr 2025
Completed
Phase Three · 12 Oct 2025