Kathonzweni Health Centre -construction And Equipping Of Laboratory

Completed GoMC-PMTS-2024-5980
Budget & Expenditure
Approved
KES 2.20M
Contract
KES 0.00
Spent
KES 1.96M
Utilisation
89.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5980
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 02 Mar 2025
Approved Requisition
Phase Two · 10 Mar 2025
Floated
Phase Two · 21 Mar 2025
Awarded
Phase Two · 12 Apr 2025
Site Handover
Phase Three · 20 Apr 2025
Not Started
Phase Three · 20 Apr 2025
Ongoing
Phase Three · 23 Apr 2025
Completed
Phase Three · 10 Sep 2025