Fencing And Gate At Kathongo Dispensary

Completed GoMC-PMTS-2024-9203
Project Description

chain link fence installation and installation of metallic gate

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.00M
Spent
KES 1.00M
Utilisation
50%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9203
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start26 Nov 2024
  • End26 Nov 2025
Timeline
Cabinet Paper Approved
Phase One · 23 Sep 2024
Approved Requisition
Phase Two · 25 Sep 2024
Floated
Phase Two · 24 Oct 2024
Awarded
Phase Two · 26 Nov 2024
Site Handover
Phase Three · 29 Nov 2024
Not Started
Phase Two · 29 Nov 2024
Ongoing
Phase Three · 06 Jan 2025
Completed
Phase Three · 09 May 2025