Mavindini Ctti Dormitory

Completed GoMC-PMTS-2024-1955
Project Description

Construction of a dormitory

Budget & Expenditure
Approved
KES 3.43M
Contract
KES 3.26M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (1 photos)
Mavindini Ctti Dormitory With A Capacity Of 40 Beds In Mavindini Ward Fy2024/25
Mavindini Ctti Dormitory With A Capacity Of 40 Beds In Mavin
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1955
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateTechnical Training
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start05 Jan 2024
  • End05 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 25 Oct 2023
Approved Requisition
Phase Two · 07 Nov 2023
Floated
Phase Two · 29 Nov 2023
Awarded
Phase Two · 05 Jan 2024
Site Handover
Phase Three · 19 Jan 2024
Not Started
Phase Two · 19 Jan 2024
Ongoing
Phase Three · 12 Feb 2024
Completed
Phase Three · 12 Sep 2024