Kathulumbi Ctti Twin Workshop

Completed GoMC-PMTS-2024-7952
Project Description

Construction of a twin workshop

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 2.85M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7952
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateTechnical Training
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Dec 2024
  • End11 May 2025
Timeline
Cabinet Paper Approved
Phase One · 11 Sep 2024
Approved Requisition
Phase Two · 01 Oct 2024
Floated
Phase Two · 11 Nov 2024
Awarded
Phase Two · 07 Jan 2025
Site Handover
Phase Three · 20 Dec 2024
Not Started
Phase Two · 20 Dec 2024
Ongoing
Phase Three · 20 Jan 2025
Completed
Phase Three · 05 May 2025