Ngaani Ecde

Completed GoMC-PMTS-2024-1837
Project Description

Construction of one classroom

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.89M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1837
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start07 Jan 2025
  • End07 Jun 2025
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Floated
Phase Two · 11 Dec 2024
Awarded
Phase Two · 07 Jan 2025
Site Handover
Phase Three · 14 Jan 2025
Not Started
Phase Two · 14 Jan 2025
Ongoing
Phase Three · 31 Jan 2025
Completed
Phase Three · 27 May 2025