Muluti Ecde

Completed GoMC-PMTS-2024-2948
Project Description

Construction of two classrooms

Budget & Expenditure
Approved
KES 3.20M
Contract
KES 3.04M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2948
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start11 Dec 2024
  • End11 May 2025
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Floated
Phase Two · 08 Nov 2024
Awarded
Phase Two · 11 Dec 2024
Site Handover
Phase Three · 19 Dec 2024
Not Started
Phase Two · 19 Dec 2024
Ongoing
Phase Three · 23 Jan 2025
Completed
Phase Three · 05 May 2025