Opening Of Kwa Mbwika-ivingoni School-kwa Kimilu Road

Completed GoMC-PMTS-2024-5726
Project Description

Road opening,grading, gravelling, construction of culverts excavation and filling of structures along Kwa Mbwika-Ivingoni School-Kwa Kimilu road

Budget & Expenditure
Approved
KES 980.0K
Contract
KES 952.2K
Spent
KES 952.2K
Utilisation
97.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5726
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start23 Feb 2024
  • End29 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Oct 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 22 Dec 2023
Awarded
Phase Two · 20 Feb 2024
Site Handover
Phase Three · 20 Mar 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 23 Mar 2024
Completed
Phase Three · 14 Mar 2024