Support To Groups – Kilungu

Completed GoMC-PMTS-2024-3230
Project Description

– Purchase of 15 (100-seater) Tents and Chairs

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3230
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateGender, Children and Social Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Floated
Phase Two · 07 Nov 2024
Awarded
Phase Two · 19 Dec 2024
Site Handover
Phase Three · 19 Dec 2024
Not Started
Phase Three · 19 Dec 2024
Ongoing
Phase Three · 19 Dec 2024
Completed